某某集團鍋爐鋼結構吊裝方案(doc 28頁)
目錄
一、編製說明..................................................1
二、編製依據..................................................1
三、工程概況..................................................1
3.1 鍋爐鋼架結構形式、總重及外形尺寸..................................................1
3.2 鍋爐鋼架組件劃分..................................................1
3.3 各組件規格、尺寸及重量見下表所示:..................................................3
四、結構吊裝的工藝要求..................................................8
4.1吊裝方法..................................................8
五、吊裝施工準備..................................................10
5.1施工技術準備:..................................................10
5.2施工現場準備:..................................................10
六、鋼架吊裝順序..................................................10
6.1 各片鋼架吊裝程序..................................................10
6.2 具體的吊裝順序及方法..................................................12
6.3前後頂板梁的吊裝(帶吊掛裝置)..................................................12
七、鋼架柱片吊裝時的受力分析..................................................12
7.1吊車吊裝能力核算..................................................12
7.2 抬吊時抬尾吊車所用吊裝索具的選擇計算..................................................13
7.3 250噸吊車單獨受力承載時..................................................14
7.4 各片鋼架柱片吊裝計算荷重及吊裝幅度..................................................15
八、鋼架柱片攬風繩及錨點的選擇..................................................16
九、頂板組件吊裝索具選擇計算..................................................16
9.1 計算荷重..................................................16
9.2 繩扣和頂板梁間的夾角計算..................................................16
9.3 吊裝索具設置及受力計算..................................................16
9.4 吊裝索具選擇..................................................17
9.5 吊耳選擇..................................................17
十、吊車行走及站位處的地麵處理..................................................19
十一、HSE作業指導書..................................................19
11.1HSE承諾..................................................19
11.2HSE方針、目標..................................................19
11.4鋼架吊裝風險識別..................................................20
11.5風險消減措施..................................................20
11.6應急責任..................................................22
11.7環境因素..................................................22
11.8保證和監督措施..................................................22
十二、資源需求計劃..................................................23
12.1 人力計劃..................................................23
12.2施工機械需求計劃..................................................23
12.3.材料計劃..................................................24
十三、附圖:組片鋼結構吊裝平麵布置圖..................................................25
一、編製說明
為了能夠順利、安全、高效的完成鍋爐結構吊裝的施工任務,使用戶滿意,現根據鍋爐鋼架安裝施工技術方案中鋼架的組合方式編製此《鍋爐鋼架吊裝施工技術方案》。
2、編製依據
2.1 鍋爐本體圖紙22.1211.585-588、22.1213.151 版次0版
2.2 《電力建設施工及驗收技術規範》(鍋爐機組篇)DL/T5047-95
2.3 《鍋爐鋼架安裝施工技術方案》
2.4 《電力建設安全工作規程》(火力發電廠部分)DL5009.1-92
2.5 《公司常用吊車性能表》(中油吉林化建股份有限公司)
2.6 《吊車性能表》(日本神鋼CKE2500型)
2.7 《工程建設安裝工程起重施工規範》HGJ20201-2000
2.8 《石油化工吊裝手冊》(上、下冊)
2.9 《大型設備吊裝工程施工工藝標準》SH/T 3515-2003
..............................