Expectations
1) A manufacturing responsible cross-functional team must be used to develop the production control plan.
2) The pre-launch control plan must be prepared per section 6 of the Chrysler-Ford-General Motors
Advanced Product Quality Planning Manual and Control Plan Reference Manual.
3) Special characteristics from the process and design FMEAs, the customer and other sources
must be clearly identified on the production control plan.
4) Inspection plans must be definied for all material and engineering specifications.
5) Flow chart operations and their desired product and process characteristic specifications must be
listed on the production control plan.
6) Data must be developed to show the direct relationship between special characteristics and their
controlling process parameters.
7) Gages and test equipment to be used during production must be identified on the
production control plan.
8) Evidence must be available to show that gages and test equipment identified on the production
control plan are accurate, discriminant, repeatable and reproducible.
9) The customer must be given the opportunity to approve the production control plan.
10) Documented measurement procedures, techniques and datums must be referenced
on the production control plan.
11) Reaction plans must specify the containment and corrective actions necessary to avoid producing
nonconforming products or operating out of control.
12) Control methods must address the requirement to produce product characteristics within specification.
13) Current controls listed in the process FMEA must be consistent with those listed on the production
control plan.
14) Reaction plans must be written so the operator can understand and implement them.
15) Statistical control methods must be documented on the production control plan.
16) Control methods and reaction plans must be updated to address any issues and lessons learned
during the production trial run, including countermeasures for known capability problems.
17) Appropriate sample sizes and frequencies must be documented on the production control plan.
..............................
1) A manufacturing responsible cross-functional team must be used to develop the production control plan.
2) The pre-launch control plan must be prepared per section 6 of the Chrysler-Ford-General Motors
Advanced Product Quality Planning Manual and Control Plan Reference Manual.
3) Special characteristics from the process and design FMEAs, the customer and other sources
must be clearly identified on the production control plan.
4) Inspection plans must be definied for all material and engineering specifications.
5) Flow chart operations and their desired product and process characteristic specifications must be
listed on the production control plan.
6) Data must be developed to show the direct relationship between special characteristics and their
controlling process parameters.
7) Gages and test equipment to be used during production must be identified on the
production control plan.
8) Evidence must be available to show that gages and test equipment identified on the production
control plan are accurate, discriminant, repeatable and reproducible.
9) The customer must be given the opportunity to approve the production control plan.
10) Documented measurement procedures, techniques and datums must be referenced
on the production control plan.
11) Reaction plans must specify the containment and corrective actions necessary to avoid producing
nonconforming products or operating out of control.
12) Control methods must address the requirement to produce product characteristics within specification.
13) Current controls listed in the process FMEA must be consistent with those listed on the production
control plan.
14) Reaction plans must be written so the operator can understand and implement them.
15) Statistical control methods must be documented on the production control plan.
16) Control methods and reaction plans must be updated to address any issues and lessons learned
during the production trial run, including countermeasures for known capability problems.
17) Appropriate sample sizes and frequencies must be documented on the production control plan.
..............................
用戶登陸
質量認證熱門資料
質量認證相關下載
- 非金屬材料材質質量認證(pdf 4
- IATF16949質量手冊(pdf 48頁)
- ISO14000環境管理體係介紹(ppt
- TS16949講義2002版(PDF 34頁)
- ISO14001環境管理體係標準及環
- ISO9000:2000版培訓教案(PPT
- ISO/IEC國家合格認可證書(pdf
- 8000B樣本培訓資料(pdf 32頁)
- ISO9000族標準培訓教程(ppt 26
- ISO9000質量管理體係標準的核心
- TL9000認可方案(pdf 13頁)
- 社會責任SA8000管理係統程序(d
- 消費品行業PCF認證(英文版)(pd
- 17025檢驗和校準實驗室的能力的
- ISO14000環境管理體係標準簡介